Institute of Ocean Sciences Electrical Maintenance Standing Offer

Status: Current
Scheduled Start Date: February 1, 2026
Scheduled Completion: April 30, 2029
Location: Victoria
Contractors: Island Technical Installations
Project hours: 8,600

Maxwell Lake Treatment Plant

Status: Current
Scheduled Start Date: April 1, 2026
Scheduled Completion: April 30, 2027
Location: Salt Spring Island
Contractors: Prep Energy
Project hours: 2,225

Hyatt Centric Old Town Hotel

Status: Current
Scheduled Start Date: August 1, 2025
Scheduled Completion: March 31, 2027
Location: Victoria
Contractors: Fettback & Heesterman
Project hours: 27,000

Kiska Multi Residential

Status: Current
Scheduled Start Date: June 15, 2025
Scheduled Completion: December 15, 2026
Location: Duncan
Contractors: Aurora Electric
Project hours: 16,200

SmartStop Storage Facility

Status: Current
Scheduled Start Date: September 22, 2025
Scheduled Completion: September 17, 2027
Location: Victoria
Contractors: Houle Electric
Project hours: 7,600

Horizon Residential Development

Status: Current
Scheduled Start Date: August 1, 2025
Scheduled Completion: February 28, 2027
Location: Langford
Contractors: Aurora Electric
Project hours: 23,000

Harbour Hills Apartments

Status: Current
Scheduled Start Date: August 1, 2025
Scheduled Completion: December 31, 2026
Location: Nanaimo
Contractors: Aurora Electric
Project hours: 27,461

Campus View Affordable Housing

Status: Current
Scheduled Start Date: December 1, 2025
Scheduled Completion: March 31, 2028
Location: Victoria
Contractors: Thomis Electric
Project hours: 20,000

CFB Esquimalt DND G-Jetty Repair

Status: Current
Scheduled Start Date: January 1, 2026
Scheduled Completion: December 31, 2026
Location: Esquimalt
Contractors: E.H. Emery Electric
Project hours: 4,000

Nanaimo Regional General Hospital Cancer Centre SW Parkade

Status: Current
Scheduled Start Date: September 1, 2025
Scheduled Completion: July 31, 2026
Location: Nanaimo
Contractors: Fettback & Heesterman
Project hours: 3,500

Nanaimo Regional General Hospital Cancer Centre Security

Status: Current
Scheduled Start Date: January 1, 2027
Scheduled Completion: December 31, 2027
Location: Nanaimo
Contractors: Houle Electric
Project hours: 11,000 (99,220 project total)

Chown Place Phase 2

Status: Current
Scheduled Start Date: May 1, 2025
Scheduled Completion: November 30, 2027
Location: Victoria
Contractors: ARRM Electric
Project hours: 20,000

617 Government Street Lifecycle Expansion

Status: Current
Scheduled Start Date: April 1, 2025
Scheduled Completion: September 30, 2026
Location: Victoria
Contractors: Sasco Contractors
Project hours: 6,000

Cowichan District Hospital Replacement Project

Status: Current
Scheduled Start Date: August 1, 2023
Scheduled Completion: December 31, 2026
Location: Duncan
Contractors: Houle Electric, Thomis Electric
Project hours: TBD

Ladore Dam Spillway Project

Status: Current
Scheduled Start Date: April 8, 2025
Scheduled Completion: December 31, 2027
Location: Campbell River
Contractors: Houle Electric
Project hours: TBD

Telus Ocean Building

Status: Current
Scheduled Start Date: February 1, 2023
Scheduled Completion: August 30, 2026
Location: Victoria
Contractors: Houle Electric
Project hours: 36,000

Strathcona Gardens Rec-Create

Status: Current
Scheduled Start Date: June 1, 2024
Scheduled Completion: September 30, 2026
Location: Campbell River
Contractors: Houle Electric
Project hours: 14,000

Starlight Meaford Residences Build

Status: Current
Scheduled Start Date: June 1, 2024
Scheduled Completion: November 30, 2026
Location: Langford
Contractors: Sasco Contractors
Project hours: 20,000

West Summit Apartments

Status: Completed
Scheduled Start Date: June 1, 2024
Scheduled Completion: December 31, 2025
Location: Langford
Contractors: Aurora Electric
Project hours: 32,715

Tillicum Corner Mixed Use Building

Status: Completed
Scheduled Start Date: October 15, 2024
Scheduled Completion: December 31, 2025
Location: Victoria
Contractors: Aurora Electric
Project hours: 35,000

DCC Rocky Point Main Gate Project

Status: Current
Scheduled Start Date: November 1, 2024
Scheduled Completion: November 1, 2026
Location: Victoria
Contractors: E.H. Emery Electric
Project hours: 3,500

Victoria General Hospital Nurse Call System Upgrade

Status: Current
Scheduled Start Date: February 1, 2025
Scheduled Completion: February 28, 2026
Location: Victoria
Contractors: Thomis Electric
Project hours: 5,600

Saanich Fire Station 2

Status: Current
Scheduled Start Date: December 1, 2023
Scheduled Completion: April 30, 2026
Location: Saanich
Contractors: Canem Systems
Project hours: 8,000

Nanaimo Correctional Centre

Status: Completed
Scheduled Start Date: November 28, 2020
Scheduled Completion: November 22, 2025
Location: Nanaimo
Contractors: Canem Systems
Project hours: 108,000